Introduction : The purpose of this methodology is to measure physically the x section of the road on ground
Procedure : The following procedure to be adopted while taking physical measure :
- The sample shall be taken on random basis
- First lot of sample shall be taken by Independent Engineer
- Start from outer side
- First measure physically the width of drain
- Then measure the width of the service road, separator, main carriage way and median
- Continuously physically measure the length across the road width as stated above in each and every Km.
- Compare each with the required TCS
Precaution :
- Road should be barricaded by the safety cone
- Two flagmen should be deployed with red flag to direct the traffic